At Six Brothers Concrete Pumping, we believe a successful pour isn't just about getting concrete on the ground. It's about protecting your crew, protecting our equipment, keeping the job moving, and planning ahead before a problem happens.

START AT THE FARTHEST POINT

WORK BACK TOWARD THE PUMP

Whenever jobsite conditions allow, our preferred placement method is to start at the farthest practical point of the pour and work back toward the concrete pump.

WHY WE DO IT THIS WAY

PROTECT THE FINISHERS

When a pour starts close to the pump and works farther away, the finishers naturally begin working behind the placement crew.

As the boom continues extending farther out, those finishers can end up underneath or within the working area of the boom.

By starting at the farthest point and working back toward the pump, the finishing crew stays behind the placement operation and on the opposite side of the active boom whenever possible.

People and heavy equipment should never occupy the same space when it can be avoided.

 

START WITH THE LONGEST REACH

A concrete placing boom carries significant weight and forces while pumping.

Starting close and continually moving farther away means increasing the reach as the pour progresses.

We prefer to establish the longest and most demanding reach first, then progressively shorten the boom and work our way back toward the machine.

 

PLAN FOR THE UNEXPECTED

Concrete pumps are large pieces of mechanical and hydraulic equipment.

Even well-maintained equipment can experience an unexpected problem.

Keeping finishers and other workers out of the boom's operating area reduces unnecessary exposure if something unexpected occurs.

Safety isn't about expecting something to fail. It's about planning the job so people are protected if it does.

 

ALWAYS HAVE A PLAN B

Starting at the farthest point also gives the job another important advantage.

If the pump develops a mechanical problem during the pour, we're working our way back toward the pump and generally toward areas with better access.

Depending on the jobsite, that may give the contractor additional options to reposition mixer trucks, tailgate concrete, or complete portions of the pour another way.

Starting close and working farther into restricted areas can do the opposite. The job may become harder to access exactly when another option is needed.

OUR POUR PHILOSOPHY

START FAR

WORK BACK

KEEP PEOPLE CLEAR

KEEP ACCESS OPEN

 

ALWAYS HAVE A BACKUP PLAN

The finishing crew knows finishing.

The concrete crew knows concrete.

Our operators know their pumps.

When our operator recommends a placement sequence, there is a reason behind it. We ask our customers and finishing crews to work with the operator so everyone can complete the job safely and successfully.

SIX BROTHERS CONCRETE PUMPING

Emergency pumping is commonly used for:

  • We don't just pump concrete.

  • We plan the pour.

  • We protect the people.

  • We finish the job.


We Are Delivering The Best Customer Experience

Lets work together. Call 713-965-4701 to get on the schedule.

About

We provide BOOM CONCRETE PUMPING services to the greater HOUSTON area.  Each pump can move up to 200 yards per hour.  If you need more, we can employ more than one pump to the project.

713-965-4701
Office@six-brothers-concrete-pumping.com
Houston, TX

Links

Contact Six Brothers

Call 713-965-4701 or Fill Out This Form

Please fill the required field.
Please fill the required field.